Approve a Budget Change
In the Administration Tools (Cost > Cost Settings > Settings tab) select the 'Notify users when approval requested' check box to notify users via email when an approval is requested. For more information, see Cost Control.
Budget change approvals are done from the Budget Change Details page. You are redirected to this page when you click the change number in the email notification or from the Items Pending Approval section.
Budget has a locked in rate:
- Approving budget change with non-zero line items will lock in an exchange rate for the budget change. The exchange rate used will depend on the budget change approval setting.
- Approving budget change with zero line items will not lock in an exchange rate.
Budget has no locked in rate:
- The first non-zero budget change that you approve will lock in the rate for the budget as well as the budget change. The exchange rate used will depend on the budget change approval setting.
To approve a budget change
- Open the Budget Details page.
- Click the Budget Changes tab.
- Click the change number of the budget change you wish to approve.
- Click Approve.
- Enter an approval date or click the date link to enter today's date.
- Click Approve.
The Budget Change Details page is displayed.
A confirmation message is displayed.
Once a Budget Change has been approved it can no longer be deleted, but it can be voided if necessary.