Add Cost Estimates

As many assumptions as necessary can be added to each category. These segments make up the sum of the category.

To create category assumptions

  1. Go to the desired scenario.
  2. For more information, see Access Project Scenarios.

  3. In each respective category, click the next available line and enter a category assumption.
  4. In the Estimate column, enter the estimated cost for this item.
  5. Costs can be entered with any of the different units of measure listed below. Toggle between the options by clicking the unit of measure.

      LS = Lump Sum

      UC = Unitized Cost

      SF = Square Feet

      F = Formula

*There are six tasks for creating scenarios that need to be following in sequence. This is task 3 of 6. The next task is Adjust Schedules.