Commitment and Budget Control Validations
Cost Entity |
Setting |
Validation |
Expression |
---|---|---|---|
Commitment Invoices |
General Settings |
The total value of actuals received to date plus the commitment invoice amounts may be equal or less than the current contract value, but they cannot exceed the current contract value. |
Actuals Received + Invoice Amount MUST < = Current Contract Value |
If, the current contract value is negative |
Actuals received to date plus the commitment invoice amount must be greater than or equal to the current contract value. |
Actuals Received + Invoice Amount MUST > = Current Contract Value |
|
If, commitment control setting is Uncontrolled, the commitment is checked against the current budget |
The total value of actuals received to date plus the current invoice amount must be less than or equal to the current budget. |
Actuals Received + Invoice Amount MUST < = Current Budget |
|
If, the budget is negative |
Actuals received to date plus this Invoice Amount must be greater than or equal to the Current Budget. |
Actuals Received + Invoice Amount MUST > = Current Budget |
|
Commitments |
General Setting (When a commitment is added, Trimble Unity Construct checks the amount against the budget ) |
The sum of the current commitments plus the commitment must be less than or equal to the current budget. |
Current Commitments + Commitment Amount MUST < = Current Budget |
If, the current budget is negative |
The sum of current commitments and the commitment must be greater than or equal to the current budget. |
Current Commitments + Commitment Amount MUST > = Current Budget |
|
Commitment Changes |
General Setting (When a commitment change is added, Trimble Unity Construct checks the amount against the budget) |
The total value of the current contract value plus the commitment change amount must be greater than or equal to actuals received to date.
|
Current Contract Value + Invoice Amount MUST > = Actuals Received |
The total current commitments plus the commitment change must be less than or equal to the current budget |
Current Commitments + Commitment Change MUST < = Current Budget |
||
If, actuals received is negative |
The current contract value plus the commitment change must be less than or equal to actuals received. |
Current Contract Value + Invoice Amount MUST < = Actuals Received |
|
If, current budget is negative |
The sum of current commitments plus the commitment change must be greater than or equal to the current budget. |
Current Commitments + Commitment Change MUST > = Current Budget |
|
General Invoices |
General Setting: (When a general invoice is applied, Trimble Unity Construct checks the invoice against the budget) |
The sum of the actuals received to date plus the Invoice amount must be less than or equal to the current budget. And The sum of current commitments to date plus the invoice must be less than or equal to the current budget. |
Actuals Received + Invoice amount MUST < = Current Budget And Current Commitments + Invoice Amount MUST < = Current Budget |
If, the current budget is negative |
The combined amounts of the actuals received plus this invoice amount And the current commitments plus the invoice amount must be greater than or equal to the current budget. |
Actuals Received + Invoice amount MUST > = Current Budget And Current Commitments + Invoice Amount MUST > = Current Budget |
|
Budget Change |
General Setting |
The combined current budget plus the budget change amount must be greater than or equal to both the current commitments and actuals received: |
Current Budget + Budget Change MUST > = Current Commitments And Current Budget + Budget Change MUST > = Actuals Received |
If, the sum of the current budget and the budget change is negative |
The combined amount of the current budget and the budget change must be less than or equal to the current commitments and the actuals received |
Current Budget + Budget Change MUST > = Current Commitments And Current Budget + Budget Change MUST > = Actuals Received |