Manage Schedule Baseline

The baseline is the planned, ideal roadmap for the project schedule. In order to give you a point of reference for measuring deviations to the baseline, a baseline should be saved after the schedule has been finalized but before the project gets underway. You can baseline the entire schedule at one time or subsets of the schedule as they are completed, such as the design tasks, construction tasks, or close-out tasks. Baselines can only be saved after the task(s) has been activated. A snapshot is automatically created upon saving the baseline.