Request Budget Change Approval

Based on permissions granted to you by the e-Builder Administrator, some budget changes may require approval before the change is accepted into the budget. A budget change approval request can be made while adding a budget change, but you may have also chosen to record the change and save the approval request for later. It is also possible that different people are involved in this process and it is now your responsibility to make the budget change approval request.

To request a budget change approval

  1. Go to the Budget Details page.
  2. For more information, see Access the Budget Details Page.

  3. Click the Budget Changes tab.
  4. Click the change number of the budget change you wish to request approval for.
  5. The Budget Change Details page display.

  6. Click Request Approval.