Schedule Mode

The Scheduling Mode choice will dictate how e-Builder will calculate either the task's Duration or Work, or a resource’s Units.

When you see the following words, interpret them as:

  • Fixed: Set by a User
  • Duration: Days
  • Work: Hours
  • Units: % of a Resource’s Work Day that are assigned to a task