Make Commitment Change Pending

The Pending status is a way to communicate to all users that a Commitment Change is expected but not finalized. For example, a verbal confirmation of a contract that is awaiting final signatures may qualify as a pending change. If the project cost summary view is configured to display the corresponding columns, this status change will be reflected there.

To change the status of a commitment change to pending

  1. Go to the Commitment Change Details page.
  2. For more information, see Access the Commitment Change Details Page.

  3. Click Make Pending.
  4. The Return to Draft button appears which allows you to rescind this action if necessary.